INFORMATION on the operation costs of investment in the
Economic Zone Nova Topola
INFORMATION on the operation costs of investment in the Economic Zone Nova Topola
1. Construction
Procedure | Type of cost | Amount (in BAM) |
Amount (in EUR) |
Location approval1 | Administrative fee | 20.00 | 10.23 |
Site visit | 35.00 | 17.90 | |
Water guidelines (if necessary) | 75.00 | 38.35 | |
Elaboration of the urban planning and technical approvals (external service of the authorized legal entity) | 1,500-2,000 | 766.94-1,022.58 | |
Construction permit2 | Administrative fee | 80.00 | 40.90 |
Elaboration of technical documentation – per m2 of the facility that is being constructed (external service of the authorized legal entity) | 12 – 15 | 6.14 – 7.67 | |
A proof for issuing the Environmental permit (external service of the authorized legal entity) | 1,500-2,500 | 766.94-1,278.23 | |
Water approval (if necessary) | 150.00 | 76.69 | |
Rent – per m2 of useful facility surface (single-payment) | 34.50 | 17.64 | |
Contribution for the cadaster | 0.3% estimated value of the construction works | ||
Fire protection compliance | 100 – 200 | 51.13 – 102.26 | |
Staking out of the facility | 100.00 | 51.13 | |
Environmental permit3 | Administrative fee | 35.00 | 17.90 |
Use permit4 | Administrative fee | 80.00 | 40.90 |
Technical review | BAM 350 for facility with surface of 50 m2 + BAM 1.50 for each additional m2 of the facility(maximum BAM 10,000) | EUR 178.95 for facility with surface of 50 m2 + EUR 0.77 for each additional m2 of the facility (maximum EUR 5,112.92 EUR) |
1 Deadline for resolving: 7 days
2 Deadline for resolving: 5 days
3 Deadline for resolving: 45 days
4 Deadline for resolving: 15 days
2. Establishment / registration of a company
Registration of a company: from BAM 172.20 / EUR 88.04 (minimum capital contribution: BAM 1 / EUR 0.51)
Registration of an entrepreneur: BAM 30.00 / EUR 15.34 (BAM 0 / EUR 0 on the first registration)
3. Land purchase
No. | Purpose | Price (BAM/m2)1 |
Price (EUR/m2) |
1 | Services, crafts and small plants | 8.00 | 4.09 |
2 | Commercial activities | 30.00 – 50.00 | 15.34 – 25.56 |
3 | Petrol stations | 80.00 | 40.90 |
4 | Warehousing | 8.00 | 4.09 |
5 | Industrial, energy and other processing capacities | 1.00 | 0.51 |
6 | Production facilities | 1.00 | 0.51 |
9 | Storage facilities | 8.00 | 4.09 |
1 Note: Presented prices include the costs of regulation of construction land.
4. Utility services
Price / consumer type | BAM | EUR | ||
Households | Legal entities | Households | Legal entities | |
Fixed (monthly) | 4.70 – 66.15 | 2.40 – 33.82 | ||
Variable
(per m3 – based on the consumption) |
2.10 | 3.18 | 1.07 | 1.63 |
* Note: + VAT (17%)
Service | Unit | Price in BAM (with VAT) | Price in EUR (with VAT) |
Waste collection by container truck | 1,1 m3 | 72.39 | 37.01 |
Waste collection by container truck | 5 m3 | 246.25 | 125.91 |
Waste collection by grapple truck | – | 321.19 | 164.22 |
Waste collection by special vehicle | – | 171.30 | 87.58 |
Waste collection for households | m2 | 0.25 | 0.13 |
Waste collection for crafts 1 | m2 | 0.85 | 0.43 |
Waste collection for crafts 2 | m2 | 1.29 | 0.66 |
Waste collection for other busines activities | m2 | 0.63 | 0.32 |
The price of electricity for small customers – other consumption varies in a range of 0.0829 -0.1460 BAM/kWh.
Price for business entities: 138 BAM/MWh , i.e. 70.56 EUR/MWh
The specific price of the connection varies in relation to the needs of investors and it can be in the range of BAM 575.62 – 2,125.56, or EUR 294.31 – 1,086.78 (in case of the standard type of connection), the construction of a metering point depending on the number of connections of users in the range of BAM 240.64 – 14,992.24, or EUR 123.04 – 7,665.41. Fees for connection of end customer facilities are determined by the Regulatory Commission of the Republic of Srpska.
The price of the connection depends on the needs of the investor (project documentation and the size of the pipe profile for both the connection to the water- supply and sewerage network, as well as the used material), ranging from BAM 702.00 – 7,371.00, or EUR 358.92 – EUR 3,768.73 for the water-supply network and connection to the sewerage network, depending on the profile of the connecting pipe in the range of BAM 468.00 – 1,638.00, or EUR 239.28 – 837.50.
5. Workforce
No. | Cost | BAM | EUR |
1 | The lowest salary | 900.00 | 460.16 |
2 | Average gross salary | 1,575.00 | 805.28 |
3 | Average net salary | 1,057.00 | 540.44 |
4 | Non-taxable income | 1,000.00 | 511.29 |
5 | Income tax | 8% | |
6 | Contributions | 31% on gross salary (18.5% – retirement and disability insurance, 10.2% – health insurance, 1.7% children insurance, and 0.6% – unemployment insurance) |
CONTACT
City Administration of the City of Gradiška
Vidovdanska 1a, 78400 Gradiška
Republic of Srpska, Bosnia and Herzegovina
Mayor:
Telephone: +387 51 810 353
Fax: +387 51 814 689
E-mail: gradonacelnik@gradgradiska.com
Head of Department for Development and International Projects:
Telephone: +387 51 810 333
E-mail: darko.vrhovac@gradgradiska.com
Center for Investors:
Telephone: +387 51 810 333
E-mail: darko.vrhovac@gradgradiska.com